Act III for the Jones Playhouse

“One beam. One damn beam.”

Anne Stewart, general manager for production at the School of Drama, marvels over the troubles caused by a massive hunk of wood that supported the UW’s Playhouse Theatre roof for most of the theatre’s 78-year history. The beam’s low clearance limited the incline of the seating bowl, complicated lighting, and affected acoustics. “It really impeded what you could do,” says Stewart.

Thanks to a major renovation completed this year, that pesky beam has now been moved. More important, all major building systems have been upgraded, and safety issues—including asbestos abatement and a seismic upgrade—have been addressed. The theatre, located at 4045 University Way NE, officially reopens October 30 as the Floyd and Delores Jones Playhouse. A free community open house, to include tours of the building, will be held October 2.

An Intriguing History

The Playhouse dates back to 1931, when Florence and Burton James remodeled a tile warehouse as a performance space, the Seattle Repertory Playhouse.  The theatre soon housed one of the few Negro Theatre Units in the country, created as part of the Work Progress Administration's Federal Theatre Project. It also boasted one of the nation’s largest theatre education programs. The Playhouse’s controversial productions eventually led the Jameses to be investigated for un-American activities by the Canwell Committee in 1948, a dramatic chapter in the theatre’s history. (For more about the Jameses and the Seattle Repertory Playhouse, click here.)  

Jones Playhouse at the very start of the renovation  
The Playhouse was gutted, with only its outer walls remaining, at the start of the renovation. Photo by John Stamets.  

The UW purchased the building in 1950 and renovated it in 1967 under the leadership of Greg Falls, then-director of the School of Drama. The renovation brought one significant change: a switch from the existing proscenium stage, in which the performance is “framed” for the audience, to a thrust stage that brings the audience closer to the action.

Since the 1967 renovation, the theatre has seen years of constant use with no major updates. Not surprisingly, its electrical, heating, plumbing, and ventilation systems had begun to fail in recent years. It also was far from ADA (Americans with Disabilities Act) compliant, lacking even an elevator. And the building was seismically unstable, with walls of unreinforced brick. “You could grab a brick and just pull it out,” recalls Stewart, shuddering at the thought. “And those were the walls we were saving.”

In fact, the three outer walls and the gable ends were just about all that was saved from the original building. The rest was gutted, making way for systems more suitable for the 21st century.

Planning for the Next Fifty Years

In designing the renovation, long-range planning was paramount. “We didn’t want a fancy building,” explains Stewart, who served as Drama’s project manager for the renovation, “but wanted it to be durable. We put most of the money toward infrastructure.” Stewart offers the example of the electrical system. “It’s a bit overwired for our current needs, because we want the ability to add as needed later on.  We want to be sure the building will still be usable in 30 or 40 years.”

Photo of seating in the Jones Playhouse  
The seating bowl's incline brings audiences closer to the action. Photo by Frank Rosenstein.  

Designed by Seattle’s LMN Architects and built by Wick Constructors, the renovated Jones Playhouse includes natural ventilation, low-flow plumbing fixtures, and lighting that balances sustainability with theatrical functionality.  For its emphasis on sustainable design, the building received a Leadership in Energy and Environmental Design (LEED) Gold rating from the U.S. Green Building Council—the first U.S. theatre to earn this rating.

Other welcome features include improved acoustics, infrared assisted listening devices, an elevator, movable seating for wheelchair accessibility, and an expansive dressing area. There’s also a catwalk for changing the lighting—a significant improvement for lighting technicians who previously climbed tall ladders to reach the lights, sometimes balancing the ladder on theatre seats.

  photo of catwalk in the Jones Playhouse
  A new catwalk allows lighting to be changed without ladders. Photo by Frank Rosenstein.

Which gets back to that pesky ceiling beam. The catwalk would not have been possible without moving the ceiling beam, nor would the building’s improved seating configuration. Yet those improvements almost didn’t happen. Only after a major gift from Floyd Jones was the School able to move the beam and raise the roof higher.

“That allowed us to raise the seating bowl, so you’re much closer to the action and the acoustics are better,” says Stewart. “It makes the audience feel more engaged.” Raising the roof also made possible an upstairs dressing room, a more open lobby space, and larger restrooms.

A Successful Test Run

All of these features were tested when the School of Drama held its “soft opening” for the building last spring. Although the theatre’s official reopening gala is scheduled for October 30, the School presented Our Town in March as an opportunity to test the new systems and work out any kinks.

  photo of dressing room in the Jones Playhouse
  The new design includes a large dressing room for the actors. Photo by Frank Rosenstein.

Stewart likens the soft opening to an informal dinner prior to a more formal feast. “We picked Our Town for the soft opening because it’s not a technically heavy show,” explains Stewart. “We just wanted to make sure everything was working as it should. You wouldn’t renovate your kitchen and have a big Thanksgiving dinner as your first chance to try things out.”

The verdict? There were a few minor glitches but no major disasters. That’s good news, given that the season opener in October will be The Tempest, a play with many more technical demands.

"There’s a huge storm and a shipwreck, there’s magic…all kinds of different stuff,” says Stewart, thrilled with the prospect. M. Burke Walker ’70 (MA) will direct the production—particularly fitting given that Walker played the lead in the inaugural production after the last renovation in 1967.

For Stewart, the opening gala will cap more than three years of work on the project, from planning to design to construction to testing.  “I’ve been involved in a number of renovations on campus, but this is my baby,” she admits. “We couldn’t have had a better team or a better result. It’s an exciting place for our students to work. There’s nothing in this space that limits what kind of show you can do. It really gives our students all sorts of possibilities.”

Want to tour the new space? Visit during the free community open house on October 2, from 1 pm to 6 pm for a tour that includes access to backstage spaces. The Playhouse's official grand reopening is October 30, with a production of Shakespeare’s The Tempest. (Previews begin October 25.) For ticket information, contact (206) 543-4880. 

Related Stories:

Jones Playhouse: A History Filled with Drama

Gift Celebrates a Passion for Theatre

 

 

Return to Table of Contents, September 2009 issue

 



 
September 2009 issue
Table of Contents
Letter from the Dean
Act III for Jones Playhouse
Camp Spanglish for Teens
Archaeology Field School's a Gem
Dance as Social Commentary
Scandinavian Studies' Centennial
Extreme Makeover for Savery Hall
Revisiting Helen of Troy
Humanities in the Digital Age
Awards & Honors
Calendar
 
Other Links
Past Issues
Editor's Picks
Article Index
Arts & Sciences Home
 
Editor:
Nancy Joseph
nancyj@u.washington.edu
Address:
A&S Dean's Office
50 Communications Building
Box 353765
University of Washington
Seattle, WA 98195-3765
(206) 543-5340 phone
(206) 543-5462 fax

 

 

 

 

 

 

 

 

 

 

.


 

 

 

 

 

 

 

 

 

.


 

 

 

 

 

 

 

 

 

 

.


 

 

 

 

 

 

 

 

 

 

.


Bookmark and Share

Phone: 206-543-5340 Fax: 206-543-5462
50 Communications #353765, University of Washington, Seattle, WA 98195-3765
Copyright © 2009 University of Washington College of Arts & Sciences

Mission, Vision & Values   |   Facts & Figures   |   Dean Ana Mari Cauce   |   Dean's Office Directory  |  Departments & Units  |  Contact Us  | Administrative Gateway